Shortly before noon on Saturday, June 5, 1976, the Bureau of Reclamation’s Teton Dam in eastern Idaho failed during its first filling. Workers had first seen muddy water coming from the right abutment that morning. The flood ran out of the Teton River canyon and across the farm towns of the upper Snake River plain. The death toll most often cited is 11, which is low for a flood of that size. The reasons are the hour, the day of the week and warnings that local officials and sheriffs passed along by telephone, radio and patrol car. That warning was improvised and uneven, and it should not be taught as a model evacuation.

The dam: an earthfill embankment on jointed volcanic rock

Teton Dam stood on the Teton River in eastern Idaho, upstream of the towns of Newdale, Teton, Wilford, Sugar City and Rexburg. Below the canyon the Teton joins the Henrys Fork, which runs on to the Snake River. The Bureau of Reclamation designed and built the dam for irrigation storage, flood control and power generation. It was a zoned earthfill embankment roughly 300 feet high, set in a canyon cut through volcanic rock. Construction ran through the first half of the 1970s, and the embankment was essentially complete by late 1975. Reclamation was one of the most experienced dam builders in the world at the time, so the failure could not be put down to an inexperienced owner.

The site had two features that later mattered to the investigators. The canyon walls were volcanic rock with many open joints and fissures, which makes a foundation hard to seal against seepage. The impervious core of the embankment, the zone meant to hold water back, was built from windblown silt taken from the surrounding area. That material is fine-grained and has little cohesion, so it erodes easily once water starts moving through it. The designers planned to handle the rock with a grout curtain injected into the foundation. They also cut deep key trenches into the abutments above river level and filled them with core material, so that the core would be tied into the rock on each side.

None of these choices was unusual taken one at a time. Grout curtains, key trenches and silt cores had all been used successfully on other dams. The review that followed the failure looked at how they combined at this particular site. Section six covers what the reviewers concluded, and I have kept it separate from the narrative of the morning so that hindsight does not slip into the timeline.

First filling: a reservoir rising fast in the spring of 1976

A new embankment dam is loaded with its full reservoir for the first time during first filling. Until then the core, the foundation, the grout curtain and the contact surfaces between soil and rock have never carried that water pressure. Dam engineers treat first filling as a period of elevated risk for this reason. Any flaw in the seepage barrier is tested then, and it is tested while the monitoring record is still too short to show what normal looks like for that structure. A dam that leaks in its first spring gives the operator no years of baseline readings to compare against.

Filling at Teton began in late 1975. Spring snowmelt in 1976 raised the reservoir quickly. As the review reports describe it, the reservoir rose faster than the rate originally planned, and part of the reason was that the outlet works were not yet fully available to release water downstream. Reclamation approved the faster filling rate. Whether a slower rate would have changed the outcome is a question the reviewers discussed and did not settle in any way I could state cleanly. I am not offering an answer to it here, and readers who need the detail should go to the panel’s report.

By early June the reservoir was close to full. The two days before the failure produced the first visible sign that water was moving where it should not. On June 3, small springs were seen in the canyon wall downstream of the dam on the right side. As the record is generally summarized, those springs ran clear. Clear seepage was not treated as an emergency, and clear water at that stage was consistent with the kind of seepage a new dam can show. The change from clear to muddy on the morning of June 5 is what mattered, because muddy water means the flow is carrying soil out of the dam or its foundation.

Clear seepage and muddy seepage are different alarms

Seepage carrying no sediment can be within what a dam is designed to pass. Seepage carrying soil means material is being removed from the structure or its foundation, and the hole it leaves lets the flow increase. At Teton the move from clear springs on June 3 to a muddy flow on the morning of June 5 is the point where the event changed category. For an emergency manager, the useful part is the language. If the dam owner’s emergency action plan describes muddy or increasing seepage as a trigger for notification, your dispatch center needs to know that the call can arrive hours before any water reaches a road.

June 5: a muddy leak, a whirlpool and two bulldozers

On the morning of Saturday, June 5, workers at the dam found muddy water flowing from the right abutment downstream of the embankment. Over the next few hours the leaking grew and moved. A wet area and then a flowing leak appeared on the downstream face of the embankment near the right abutment, and the flow carried more material as it enlarged. Accounts also describe a whirlpool forming in the reservoir near the right abutment. That was a sign of water entering a passage through or around the embankment on the upstream side. The exact minutes differ between secondary accounts, so I give the sequence without precise times. Anyone building a training timeline should take times from Reclamation’s records and the review reports.

Reclamation crews sent bulldozers to push fill and rock into the growing hole on the downstream face. The attempt failed. As the event is commonly described, two bulldozers were caught as the ground gave way around the eroding opening and were lost, and their operators got clear. People at the site took photographs and motion picture film during the late morning. That footage is the reason the Teton failure is so widely recognized, and it remains useful in training because it shows how quickly a leak became a breach once it began to grow.

At about 11:57 a.m., the time usually given, the crest of the dam collapsed into the enlarging opening near the right abutment, and the reservoir began to pour through the breach. A large part of the embankment on the right side washed out, and the reservoir drained over the following hours. Estimates of the peak flow and of the volume released appear in various sources. I am not quoting a figure, because I cannot confirm which estimate the reviewers adopted. The interval between the first muddy leak and the breach was a matter of hours. That interval is the most important fact for the warning story that follows.

The warning: phone calls to sheriffs, radio and deputies on the roads

As the leak grew, Reclamation personnel at the dam notified local authorities downstream, including the sheriffs’ offices in the affected counties. As the record is generally summarized, those calls went out in the late morning, roughly an hour before the breach. Sheriffs and deputies then carried the warning along the roads in patrol cars. Local radio broadcast it, and residents telephoned relatives and neighbors. A good deal of the warning moved through ordinary social networks in a farming area where people knew each other and believed the people calling them.

The warning was put together on the day. As far as I can determine from the published accounts, Reclamation and the counties did not run it from a pre-written emergency action plan with inundation maps, arrival times and a tested call list of the kind a high-hazard dam is expected to have today. People made phone calls, and the people who received them made more calls and drove where they could. I am describing the general picture in the record. Anyone who needs the specifics of who called whom and when should go to the review reports and Reclamation’s own accounts. They should not rely on retellings, which tend to add precision the sources do not support.

Warning time depended heavily on distance. Communities just below the canyon mouth had little time between the breach and the arrival of the flood. Rexburg, farther down the valley, had more. Idaho Falls and points farther downstream had many hours, and American Falls Reservoir on the Snake ultimately absorbed much of the flood. Some people heard the warning early and left. Others heard it late, doubted it, stopped to gather belongings or did not hear it at all. That unevenness is why I describe the warning as partly successful, and the evidence supports that phrasing better than either a triumph or a failure.

Eleven dead: why the number is low and where it is disputed

The figure most often cited for deaths in the Teton flood is 11. It appears widely in Reclamation’s historical material and in most later accounts. Some accounts give a higher number, commonly 14. As far as I can tell, the difference comes from whether a source counts only people killed directly by the water or also deaths during the evacuation and recovery that it attributes to the disaster. I cannot point to a single authoritative publisher of the higher figure. So I treat 11 as the commonly accepted count of direct deaths and note that a higher count circulates. I have also not found a breakdown of where each person died that I trust enough to publish.

Several conditions explain why the toll was not far higher. The dam failed shortly before noon on a Saturday, when most people were awake, at home or nearby, and reachable by phone. The failure developed over several hours in full view of people who had telephones and the authority to use them. The towns closest to the canyon were small, and the larger population centers lay far enough downstream to gain time. The valley’s residents took the warnings seriously in large numbers, and accounts consistently describe people leaving on word from sheriffs, broadcasters and neighbors. Remove the daylight or the hours of visible distress and the same flood could have produced a very different count.

Damage figures are even less settled than the death toll. The flood destroyed or damaged thousands of homes and farm buildings, wrecked irrigation works, scoured farmland and killed large numbers of livestock. Published dollar estimates range from several hundred million dollars to around a billion, depending on the source, the year of the dollars and what is counted. I am not giving a single figure. Congress passed legislation in 1976 to compensate flood victims, and the federal government paid claims under it. The amounts are in the congressional and Reclamation record, which is where anyone who needs them should look.

The independent panel: internal erosion and a finding about design

Two reviews examined the failure. The Secretary of the Interior and the Governor of Idaho jointly appointed an independent panel of outside experts to determine the cause, and it reported at the end of 1976. The Department of the Interior also formed its own review group, which issued findings beginning in 1977. Both documents are public. They are the record anyone teaching this event should cite, in preference to the many summaries that compress their conclusions.

As the panel’s conclusions are generally summarized, the dam failed by internal erosion, often called piping, of the silt core material in the key trench on the right abutment. Water found a path through or along the core where it met the jointed rock, carried the erodible silt away and enlarged that path until the embankment above it collapsed. The panel discussed more than one way the initial flow path could have formed. These included water moving through open joints in the rock at the grout curtain and cracking within the core caused by how the narrow, steep-sided key trench distributed stresses. The physical evidence in the failed section had been washed away, so the panel could not establish the starting mechanism with certainty. The finding that mattered most did not depend on that point, because the panel concluded that the design had not provided adequate defenses against erosion of that core under those foundation conditions. Protective filter zones were a central part of that discussion. A properly graded filter downstream of the core can trap eroding particles before they leave the dam.

The panel’s emphasis on design rather than construction workmanship is worth keeping intact when the event is taught. As the findings are generally described, the problem was that the combination of erodible core, jointed rock, grouting that could not be relied on to seal it and key trench geometry left no dependable second line of defense once seepage began. Construction carelessness was not the issue. Construction crews and the people at the dam on June 5 are not the subject of the panel’s main conclusion, and accounts that blame them misread it.

Do not teach Teton as a planned evacuation

Because the death toll was 11, Teton is sometimes held up as a successful dam failure warning. The record does not support that framing. The warning was improvised by phone and patrol car without the inundation maps and call lists modern emergency action plans require, and it reached people unevenly. The low toll owes a great deal to a failure that happened in daylight, on a weekend, over several hours, in a sparsely populated upper valley. Teach the parts that worked, and say plainly that a night failure or a fast failure under the same arrangements would have tested them very differently.

What followed: federal guidelines, Toccoa Falls and state programs

Teton was not the only dam failure of the period. In November 1977, the Kelly Barnes Dam above Toccoa Falls College here in Georgia failed in the middle of the night after heavy rain and killed 39 people, many of them students and staff housed along the creek below. Teton exposed the federal government’s own dam engineering, and Toccoa Falls exposed the condition of thousands of non-federal dams that nobody was inspecting. Together the two failures drove the national reforms of the late 1970s. After Toccoa Falls the federal government directed the Army Corps of Engineers to inspect high-hazard non-federal dams. Georgia passed the Georgia Safe Dams Act in 1978 and created the state program that still regulates dams here.

At the federal level, the Carter administration ordered a review of federal agencies’ dam safety practices. That work produced the Federal Guidelines for Dam Safety, published in 1979 through an interagency committee, and the dam safety coordination role was assigned to the newly formed FEMA. Reclamation set up its own safety of dams program and received statutory authority under the Reclamation Safety of Dams Act of 1978 to modify its existing dams for safety reasons. Emergency action planning, meaning a written plan for detecting a developing failure, notifying downstream authorities and mapping who would be flooded, became an expected part of dam safety practice in the years that followed. The National Dam Safety Program Act of 1996 later gave the national program a firmer statutory footing.

I am describing these measures at the level of what they did, without summarizing their provisions, and the current versions differ from the originals. Guidance on emergency action plans and inundation mapping has been revised several times since 1979. The current requirements for a given dam depend on who owns it and which state or federal regulator has jurisdiction. Verify current requirements with your state dam safety program or the federal agency that owns or regulates the dam. FEMA’s National Dam Safety Program publications are the place to start.

Teaching Teton: what the warning did and did not do

The useful part of Teton for a working emergency manager is the warning chain, because the engineering lessons belong to dam engineers. The chain had two features worth copying. Reclamation staff at the dam called downstream authorities while the dam was still standing, and they did not wait for certainty that it would fail. The people who received those calls had both the authority and the means to reach the public quickly. A sheriff with deputies on the roads and a local radio station carrying the message are the same pieces a modern warning plan relies on. The difference is that today the pieces are supposed to be identified and tested before the morning they are needed.

The warning also showed problems that a modern plan should remove. No one had worked out in advance how long the water would take to reach each community. Nobody had a list of who would be flooded, and nobody had a way to confirm that each household had been reached. Warning time for the closest communities was set by how early the calls went out and how fast deputies could drive, which is the wrong dependency for the people with the least margin. Some residents did not believe the warning. That reaction is common in warnings of all kinds, and a pre-scripted message from a trusted source helps with it.

The comparison with Toccoa Falls is the one I use in teaching. That failure came at night, with little visible warning, and the dead were people asleep near the creek. Teton came in daylight after hours of visible distress. The same improvised warning arrangements produced very different outcomes because the conditions were different. A plan has to assume the worse case, and that means a failure at night, developing fast, with the dispatcher’s phone as the first and possibly only notice.

Ask what your warning depends on

Teton’s warning depended on daylight, a slow failure, working phones and deputies who could cover the roads in time. When you review a dam failure annex or an owner’s emergency action plan, list what each step depends on in the same way. Then ask what happens if the call comes at three in the morning with half the warning time. If the answer relies on someone driving door to door in the communities closest to the dam, those residents are the ones the plan protects least.

What to do at your agency

  • The county emergency manager asks the state dam safety program for its list of high-hazard dams that would flood any part of the jurisdiction, and the task is finished when that list, with each dam’s owner and regulator, is attached to the existing hazard mitigation or emergency operations plan.
  • The PSAP or dispatch supervisor pulls the notification page from the emergency action plan of each high-hazard dam on that list and confirms that the phone number the owner calls reaches a center staffed around the clock, and the task is finished when each number has been test-called and the result logged with the date.
  • The emergency manager reads the inundation map in one high-hazard dam’s emergency action plan, writes down the estimated arrival time at the nearest populated area and adds that time and the planned alerting method to the dam failure section of the existing plan, and the task is finished when the section states how the closest residents will be warned without relying on door-to-door notification.
  • The public information officer drafts a short dam failure warning message for the nearest high-hazard dam, naming the sending agency and the evacuation direction, and loads it as a template in the jurisdiction’s alerting system, and the task is finished when the template is saved and the alerting administrator has confirmed it can be sent within minutes.
  • The sheriff’s office or police operations commander adds dam failure notification to the agenda of the next scheduled shift supervisors’ meeting, covering who receives the owner’s call and which roads deputies take first, and the task is finished when the meeting notes name the units assigned to the areas with the shortest warning time.
  • The training officer adds Teton Dam and the 1977 Toccoa Falls failure to the next scheduled officer or dispatcher development session, built around the hours between the first muddy leak and the breach, and the task is finished when the session notes state that the 1976 warning was improvised and the low toll depended on daylight and lead time.

Takeaways

  • Teton Dam, a Bureau of Reclamation earthfill dam in eastern Idaho, failed during its first filling at about 11:57 a.m. on Saturday, June 5, 1976.
  • Clear springs were seen downstream on June 3, and on the morning of June 5 muddy seepage from the right abutment grew over several hours into a breach that bulldozer crews could not stop.
  • Reclamation staff notified downstream sheriffs before the breach, and deputies, local radio and residents spread a warning that was improvised and reached people unevenly.
  • The commonly cited death toll is 11, some accounts give a higher figure, and published damage estimates range widely enough that no single number should be presented as settled.
  • The low toll owes much to a daytime, weekend failure that developed over hours, and it should not be taught as the result of a planned or complete evacuation.
  • The independent review panel attributed the failure to internal erosion of the erodible silt core in the right abutment key trench and concluded that the design lacked adequate defenses against it.
  • Teton and the 1977 Kelly Barnes Dam failure at Toccoa Falls, Georgia, drove the federal dam safety guidelines of 1979, Reclamation’s safety of dams program and state programs such as Georgia’s.
  • Current emergency action plan and inundation mapping requirements vary by dam owner and regulator and should be confirmed with the state dam safety program or the owning federal agency.